Tyler
|
972cc99200
|
docs: mark SP4 partial shipped (claim drawer); tick all plan checkboxes
|
2026-06-20 12:37:31 -06:00 |
|
Tyler
|
bdc851f0f0
|
docs(sp4): per-claim detail drawer implementation plan (24 tasks, 5 phases)
|
2026-06-20 08:55:49 -06:00 |
|
Tyler
|
446a02d0a2
|
docs: mark SP3 shipped; tick all plan checkboxes
|
2026-06-20 08:25:15 -06:00 |
|
Tyler
|
763ca3d758
|
docs(sp3): put transaction_type_code on ClaimOutput (mirrors envelope convention)
|
2026-06-20 07:18:16 -06:00 |
|
Tyler
|
467087d683
|
docs(sp3): fix rule IDs (R034/R035) and BHT06 naming in plan+spec
|
2026-06-20 07:18:03 -06:00 |
|
Tyler
|
b47818883a
|
docs: add EDI features spec + implementation plan (sub-project 3, 30 tasks)
|
2026-06-20 07:14:14 -06:00 |
|
Tyler
|
b7f831e170
|
docs: tick off completed boxes in sub-project 1 plan (housekeeping)
|
2026-06-20 00:11:01 -06:00 |
|
Tyler
|
53010b89dd
|
docs: add DB + reconciliation implementation plan (30 tasks, 7 phases)
Implements the spec at docs/superpowers/specs/2026-06-19-cyclone-db-reconciliation-design.md.
Phase 1 — Backend foundation (T1-T3): SQLAlchemy dep, db.py skeleton,
PRAGMA user_version migration runner, 0001_initial.sql with 6 tables.
Phase 2 — ORM models (T4-T6): Batch, Claim, Remittance, CasAdjustment,
Match, ActivityEvent + ClaimState enum.
Phase 3 — Reconciliation pure functions (T7-T8): match() with date
window + multi-claim fallback, apply_payment/apply_reversal,
split_unmatched.
Phase 4 — Store facade refactor (T9-T12): CycloneStore replaces
InMemoryStore with same public API + list_unmatched / manual_match /
manual_unmatch; reconcile.run orchestrator wired into store.add().
Phase 5 — API additions (T13-T17): db.init() in startup,
GET /api/reconciliation/unmatched, POST /match, POST /unmatch,
parse-835 response includes reconciliation summary; TODO marker
removal verification.
Phase 6 — Frontend (T18-T26): ClaimState types, api.listUnmatched/
matchRemit/unmatchClaim, useReconciliation hook, ClaimStateBadge
primitive (7 states, same palette), Reconciliation page, sidebar
nav entry, vitest worktree exclude.
Phase 7 — Docs + smoke (T27-T30): README persistence section + DB
URL docs, tick off sub-project 1 plan boxes, full end-to-end smoke
procedure, merge to main.
Total: 30 tasks across 7 phases. TDD discipline per task with
~32 new backend tests + ~4 new frontend tests. Target after
completion: 210 backend + 7 frontend tests passing.
|
2026-06-19 20:51:31 -06:00 |
|
Tyler
|
d7ef35dd9a
|
docs: add production-readiness implementation plan (33 tasks, 4 phases)
Phases:
1. Backend (T1-T10): cyclone.store module, 6 GET routes, NDJSON streaming,
parse persistence, uvicorn 127.0.0.1 bind, full test suite run
2. Frontend (T11-T27): react-query wiring, 5 new UI primitives (Skeleton,
EmptyState, ErrorState, FilterChips, Pagination), Layout-level refetch
indicator, 5 page refactors (Claims, Remittances, Providers, ActivityLog,
Upload), 6 hooks, 3 keyframes, api.test.ts
3. Docs (T28-T32): 4 reference notes (837p, 835, x12naming, co-medicaid),
root README rewrite
4. Smoke (T33): end-to-end manual test with full acceptance checklist
Self-review included at end of plan (spec coverage table + placeholder
scan + type consistency check).
For agentic workers: superpowers:subagent-driven-development (recommended)
or superpowers:executing-plans.
|
2026-06-19 18:43:17 -06:00 |
|
Cyclone
|
5ed59ef01a
|
Add 837P parser implementation plan
- 12 tasks: project skeleton, exceptions, segments, models, payer config,
fixtures, validator, parser orchestrator, CO fixture, writer, CLI, README
- TDD throughout; each task has 4-6 bite-sized steps with full code
- Optional prodfile smoke test (skipped if docs/prodfiles absent)
- Self-review checklist confirms full spec coverage
|
2026-06-19 15:12:04 -06:00 |
|